non-stock item materials don't appear in standard cost report S_ALR_87013533

Former Member
0 Kudos

Hi Experts,

In standard cost report S_ALR_87013533, only stock-item materials appear in the hiearchy structure (included also planned cost for it).

But non-stock item materials don't appear, and the planned cost of non-stock item materials are included in responding activity.

How can we make the non-stock item material components also display in S_ALR_87013533?

Please help to advise.

Thanks and regards,

Khoa Huynh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I think you can see stock materials in report because you check the flag in Costing view for show origin. While for non-stock material such facility is not available.

This may be reason you can not see non-stock materials in costing reports.

Regards,

Mahendra

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Few days back we also faced similar issue where we were not able to see commitment cost items for non stock materials. And commitment cost items were only appearing for stock materials.

When we raised this issue to SAP, we understood following from them.

--The definition of commitment is 'Obligation to pay to a supplier'.

  Means payables in the future.(via invoice)

  But stock material means that material is already yours.

Therefore there are not payables (FI) and none commitments.

  The valuated project stock indicator is only relevant for actual costs , but not for commitments.

Regards

Tushar