Hi all,

I've a question about canceling inspection lots when using the QM-IDI interface. When an inspection lot is processed by the sub-system the table QIWL get updated (SENDSTAT=A). the status of the inspection lot is SUB.

When i than cancel the lot the field PRUEFSTAT gets value C. Now i want to make sure that this update gets to LIMS as well. But when i now perform FM QIRF_SEND_REQUIRMENTS_GET_DAT2 (with indicator  I_IND_MULTI_TRANSFER_POSSIBLE = X) i get no results. How should we handle canceled lots?