on 04-03-2012 11:23 AM
Hi All,
After all the quantities delivered of a schduling agreement, the status showing as Partially delivered, and the document is in In progress. Document type and item category used are LZ and LZN respectively. please help.
Regards
Bidhu
Hi,
Check your item category, whether item relev.for del is checked,if checked just un check and try.
Regards
Ram