on 04-03-2012 8:39 AM
Hi Experts,
I hope you all are doing well..
My client wants workflow or mail to some users at time of activity confirmation in Project.
I discussed with workflow consultant he checked in SWEL t code and told me that event is not triggering after activity confirmation.
please suggest me is there any config to trigger event when we book actual for activity? how can i we generate workflow for activity confirmation?
Please suggest me..
Thanks in advance.
Regards
Hi Sonal,
did you carry out the settting in the confirmation customizing,
Project System
Confirmation
Define Confirmation Parameters
There are two parameters (one for work, other for duration) need to be set at first.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.