Hi Experts,

Business scenario calls for issue of SFG from level2 WBS to upper WBS(L1) to make another SFG product.We have wo separate production orders for the same. production order for L2 is confirmed and GR to project. The maerial is available in project stock. When we try to issue this material to another production order of L1 wbs, we have a error message in GI as follows.

Special stock XXXX Q  L1WBS SFG of this material does not exist

Message no. M7076

Diagnosis

No special stock Q of the material (batch ) exists in storage location XXXX for L1 WBS SFG

Procedure

Make sure your entries are correct.

Do you want to display the stock overview

What is the probable step missed in configuration. Can anyone help on this.

Thanks in comprehension. Rgds

AM

Accepted Solutions (0)

Answers (1)

Answers (1)

sunil_yadav2
Active Contributor
0 Kudos

Dear AM,

your SFG material is in Project Stock under level 2 WBS so you have to transfer this material to L1 WBS. Use MB1B tcode and movement type 415 Q than enter location where material exist and where to transfer. than this problem will remove and this material will consume while confirming this activity/production order.

thanks