Dear Experts,
We are using SRM, as per the client requirements we have done some enhancement in Proces level configuration for Quotation.
New process schema is determined as expected, now there were some changes in requirements, so we wanted to keep the standard Process schema, so restored every as earlier as per the statndrd.
Checked in SPRO every thing is saved correctly, but when we run some transaction always the old Work flow /Z work flow is getting triggered when i check in SLG1,
Is there any way to refresh the tables for Process level configuration please suggest.
If you need any moreinformation please do let me know.
Regards,
Raghu