CJCO (Budget Rollforward)

Former Member
0 Kudos

A project is budgeted at 20000 with 10000 in FY2011 and 10000 in FY2012.

If Budget in FY11 overspent Example 11000, it means there is nothing to carry forward to next year as Carry Forward = Actual budget in 2011 - total assigned budget in 2011(10000 - 11000 = -1000)

Is there any way(Automatic) with the help of which budget in 2011 will become 11000 and in 2012 becomes 9000?

I know that to do this we have to post supplements and returns manually, but i want automatic way?

Please reply back.........

Thanks,

ROjer.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Rojer,

There is no automatic way to carry forward negative values to next year.

You have to do it manually (post supplements to current year and returns to the next year according to the example you gave us) or you can create one custom program which will do these posting automatically.

Thanks,

Inder

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi All,

Thanks for replying.

Yes you all were right i have tried many option to do it automatically but... nothing happened right.

I have given marks by seeing the level of details you have provided to this post.

Thanks once again,

Rojer

former_member221039
Active Participant
0 Kudos

i agree with sunil, no automatic way of transfer of budget.

once fiscal year changes, you must carryout CJCF & CJCO for projects which are budget profile activated.

thanks/srihari

sunil_yadav2
Active Contributor
0 Kudos

Dear Rojer,

As per my knowledge their is not way to automate this transfer of budget. this is done manually.

thanks

Sunil