Good Morning PS Gurus,

When the component assignment option "PurReq + WBS Element" (which is the default option) is selected in CN33 the resulting PR´s will be created with the firming indicator activate. MRP Controllers would like to create these PR´s without this firming indicator so that MRP can replace the PR´s by non-firmed planned orders. If the PR´s are firmed that is not gonna happen. They need planned orders not PR´s.

This request may sound a little bit strange but it has a reason. They can save quite some time in CN33 if they don´t have to change the default option for component assignment. As we know, they have to transfer hundreds of materials to the network every day

Please let me know if there is any configuration in the system that would allow us to create non-firmed PR´s in CN33?

Thank you!

MM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello PS GURUS,

Default firming indicators comes from MRP types of the material from Material master

Please help.

Thanks

MM