Lower level wbs plan values are not showing at header level WBS

Former Member
0 Kudos

Hi

We are not able to see any plan values at header level WBS in the report output and even there are plan values in lower level wbs but these values are not roll up to header level WBS level in the report.

This issue is happening only for one specifc project but for other projects there is no issue.

Please help us on my issue.

Thanks

Risha

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member230675
Active Contributor
0 Kudos

why you are not reconstructing the data base. All of them are giving suggestion and you are not following it, then what is the idea behind posting the query in the forum.

please reconstruct data base through CJEN and check, if the issue still exists then create report ZBPTOTUP as per note  584655.

virendra_pal
Active Contributor
0 Kudos

Check your planning profile (OPSB) and also if you have planning element requirement then this needs to be ticked in the WBS element to capture WBS level planning

Former Member
0 Kudos

WBS data is correct... and when i check the plan values in CJ40.

The values are showing in below for example:

Header level WBS - 1 = ( not roll up the below lower level WBS values )

Lower level WBS -2 = 1000 USD

Lower level WBS-3=  2000 USD

But for other project  , the lower level WBS values are rollup to header level WBS (exampe in below )

Header level WBS - 1 = 3000 USD (rollup cost from lower level WBS  )

Lower level WBS -2 = 1000 USD

Lower level WBS-3=  2000 USD

We are not able to understand why this is happend only for one specfic project.

Thanks

Risha

Former Member
0 Kudos

Try running CJEN for this particular project and then check the reports.

Former Member
0 Kudos

see whether your header level wbs element has planning element marked.

Former Member
0 Kudos

Yes.. My header level WBS elements are selected as planning element.

Former Member
0 Kudos

please help us.. the planning element check box in header level wbs is the issue or not ?

Former Member
0 Kudos

Hi

As u confirmed planning element check box was alredy selected in header level wbs element.

Have u executed CJEN, CJBN T.Codes as Gokul said and aslo check OPSB settings.

Please check and revert your comments

Regards

Former Member
0 Kudos

Hi.

Thanks.. do we need to deselect the check box in header level WBS before execute t-codes:CJEN/ CJBN ?

Please confirm

Former Member
0 Kudos

Hi

Not required,

Former Member
0 Kudos

sorry... without changes in WBS structure. what is the purpose to execute the above said t-codes ??

Former Member
0 Kudos

Who told that CJEN is run only when there is some change in the project structure?

CJEN is a tcode which can be run anytime you want. It does not have any ill effects on the system.

Former Member
0 Kudos

Ok.... we are not able to understand why this issue only for specific project.?

Former Member
0 Kudos

see if you have bottom up planning marked in plan profile. if not then you have to run total up function.

Former Member
0 Kudos

Hi

The T.codes will not harm anything, Incontinences will be removed if any.

Also check correct project OPSB settings and this project OPSB settings.

Regards

Rao

Former Member
0 Kudos

yes... we have selected the bottom up planning in plan profile. but even we have this issue only  for this project

Former Member
0 Kudos

ok try to run CJEN transaction as mentioned earlier by our frds...

Former Member
0 Kudos

refer to note 584655. hope this will solve your issue.

Former Member
0 Kudos

Hi..

We tried to use program - BPDIST00 to reconstruct the plan cost. but we are not succeed on this.

Can you please help me on my issue.. still my issue is open.

Former Member
0 Kudos

Hi,

If bottom up planning indicator is set then lower level WBS will show values for higher ones.

Check planning element indicator also. In OPSB check planning is marked, if yes then in CJ20N also , higher should be marked as planning element.

Else try to run CJEN and check report again.

Regards

Raghav

former_member384980
Participant
0 Kudos

WBS data is correct... and when i check the plan values in CJ40.

The values are showing in below for example:

Header level WBS - 1 = ( not roll up the below lower level WBS values )

Lower level WBS -2 = 1000 USD

Lower level WBS-3=  2000 USD

In the same screen go to edit>then total up> save.

then try the report.

Regards

Deepak

Former Member
0 Kudos

Have you tried doing total up in CJ40?

Former Member
0 Kudos

Using the t-code : CJR2 with excel planning option.