on 04-02-2012 8:17 AM
Hi
We are not able to see any plan values at header level WBS in the report output and even there are plan values in lower level wbs but these values are not roll up to header level WBS level in the report.
This issue is happening only for one specifc project but for other projects there is no issue.
Please help us on my issue.
Thanks
Risha
why you are not reconstructing the data base. All of them are giving suggestion and you are not following it, then what is the idea behind posting the query in the forum.
please reconstruct data base through CJEN and check, if the issue still exists then create report ZBPTOTUP as per note 584655.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check your planning profile (OPSB) and also if you have planning element requirement then this needs to be ticked in the WBS element to capture WBS level planning
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
WBS data is correct... and when i check the plan values in CJ40.
The values are showing in below for example:
Header level WBS - 1 = ( not roll up the below lower level WBS values )
Lower level WBS -2 = 1000 USD
Lower level WBS-3= 2000 USD
But for other project , the lower level WBS values are rollup to header level WBS (exampe in below )
Header level WBS - 1 = 3000 USD (rollup cost from lower level WBS )
Lower level WBS -2 = 1000 USD
Lower level WBS-3= 2000 USD
We are not able to understand why this is happend only for one specfic project.
Thanks
Risha
Hi,
If bottom up planning indicator is set then lower level WBS will show values for higher ones.
Check planning element indicator also. In OPSB check planning is marked, if yes then in CJ20N also , higher should be marked as planning element.
Else try to run CJEN and check report again.
Regards
Raghav
WBS data is correct... and when i check the plan values in CJ40.
The values are showing in below for example:
Header level WBS - 1 = ( not roll up the below lower level WBS values )
Lower level WBS -2 = 1000 USD
Lower level WBS-3= 2000 USD
In the same screen go to edit>then total up> save.
then try the report.
Regards
Deepak
Have you tried doing total up in CJ40?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.