on 04-02-2012 6:43 AM
Hello experts,
I am facing a strange problem. A user has created a PO of 1000/- then the MIGO was done.
Now, user canceled this MIGO again.Then he created MIGO again and canceled it again thereafter. Now, when he is going to do MIGO again sysem is giving error"budget exceeded". I checked the report S_ALR_87013558 first,it is showing 2000/- as assigned value. then i checked CJI3 which is showing actual value as 1000/-. I checked CJI5 which is showing 1000/- as commitment value. In PO history tab of PO ,goods receipt value is 0.00 .Then why this discrepancy is happening?
I ran CJEN,CJBN, RKABU01/RKACOR04.. but no gain...
Kindly help me to resolve the error.
Thanks & Regards
Ankur
Hi Ankur
As per your information in both times user has concelled GR document, in that there is no actuals were happened. So obviously commitment is Rs. 1000/-. But as per your information in CJI3 it is shoiwng 1000/- as actual value which is wrong.
Please check once again whether user has cancelled correct line item GR document or not?.
Regards
Rao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, Mr. Rao,
can you please tell me this FI document is posted against which entry. If the user has created only one PO of 1000/- then why the assigned value is showing 2000/- . Yes, I know it is actual+commitment=assigned but why System is restricting my user to do MIGO of my live PO of amount 1000/- .
Also, what impact FB03 has made?
please suggest..
Thanks & Regards
Ankur
Hi Ankur
1. can you please tell me this FI document is posted against which entry - You can check the FI entry details in CJI3 report or COEP table.
2. If the user has created only one PO of 1000/- then why the assigned value is showing 2000 - If user is posted FI document by giving same WBS element (PO created WBS element) then obviously this 1000/- amount as actual would reflect in the report as 2,000/- (PO CI 1000+FI doc 1000)
3. If u post GR document with same PO commitment amount (Rs.1000) system will not throw an error message while posting of GR document (GR with reference to PO). If GR amount exceeds the PO amount then system will throw an error message if budget is not available. In this case double click on error message so that u can see the exceed amount details.
Hope this will help to u and let me knwo if any.
Regards
Rao
Dear Ankur,
Hope you'll be fine.
First please tell how much budget you have on WBS
Second assigned value is the sum of (actual value and commitment), so assigned value will consume budget from WBS, in your case 2000 is consumed from budget. in S_ALR_87013558 report check the available column.
Third you have canceled/reversed all the MIGOs. so the commitment is still there as it is.
In my opinion there is no discrepancy. Please let me know if I understood you question in the right way.
Thanks & Best Regards
Mohid Javed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.