planning horizon MRP

Hi Gurus,

Planning horizon:

In OPPQ we define number of days.

Eg: Plant 2xxx. Planning horizon = 100 days.

Now, I'm expecting that if I have Planned indep requirements/sales orders beyond 100 days, MRP Run will not generate any planned orders/purchase requisitions.

TCode: MD61. created PIRs - 100 qty 03/05/2014, 03/05/2015

TCode: MD02 - Ran MRP.

TCode: MD04 - can see planned orders created on 03/05/2014 and 03/05/2015.



Did you use NETPL? I think you used NETCH during MD02 run. Delete the planned order and re-run MRP with NETPL.