cancel
Showing results for 
Search instead for 
Did you mean: 

Consignment Pick up to different plant

Former Member
0 Kudos

Hi Experts,

I have a scenario in the consignment Pick up.

Once I complete the consignment Fill up, there is a damage or general stock pull up from consignment stock. Because my production plant (plant 1) is not accepting the returns, we have different plant (plant 2) who process returns and take responsibility of returns.

Without doing transfer from plant 1, Is there any possibilities that I can directly do consignment pick up from consignment stock to return plant stock (Plant 2)

Regards

Manimaran K

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

I will test the scenario and tell you tomorrow..

Lakshmipathi
Active Contributor
0 Kudos


One thing what you can do is with the exit USEREXIT_SOURCE_DETERMINATION in the program MV45AFZB, you can force the required plant which should happen in the background though system picks up the parent plant.

But from inventory point of view, I am not sure which you should try on your own and update here.


G. Lakshmipathi

ravi_kumar100
Active Contributor
0 Kudos

Hi,

As Lakshmipathi suggested do a test cycle for the Consignment pickup and share us your solutions and suggestions.

Regards,

Ravi

Former Member
0 Kudos

hi Ravi,

Whatever stock movement from plant to plant or storage location to storage location, you can do the stock transfer.

system is checking the stock relevant storage location with combination of plant..

your scenario is not possible ,better try storage location to storage location.

logically, internally stock movement happening through storage location only not plant

---Dinesh

Former Member
0 Kudos

Hi Dinesh,

Cant we do consignment pick order to a different plant?

Lakshmipathi
Active Contributor
0 Kudos


I will be happy if you test this scenario and update here whether system is allowing to change the plant in consignment pick up order, so that it will be helpful to all.


G. Lakshmipathi

Former Member
0 Kudos

Sorry, I cant test now.

I'm into Phase-2, Before I go to realization this has to be come up with solution.

No server access too...

Former Member
0 Kudos

Hi Manimaran,

u can do the same in the following way

* Extend the material from plant1 to plant2

* Stock transfer order from plant 1 to plant2

then process asusual consighnment process from plant2 instead of plant1

Regards,


Raviteja

Former Member
0 Kudos

Hi Ravi,

The issue is after Consignment fill up. How it will be useful if you stock transfer order. This Material is already extended to both the plants and I already done the Consignment Fill up from Plant 1, Now I have to perform Consignment pickup to a different plant (Plant 2).

Awaiting for your response.

Regards

Manimaran K

Former Member
0 Kudos

Hi,

before doing consighment fill up ( placking the stock @ customer end) .

Extend the material to Plant-2 and do Consighnment issue  for the same.

Specify the plant-2 while creating the consighnment pickup & process the same.

hope it will work.

Regards,

Raviteja

Former Member
0 Kudos

Hi,

As we know the process are related in following sequence.

Consignment - Fillup, Pickup (If needed), Issue and Return (If needed).

I have a material which is extended for both plant.

1) Fill up is already completed from Plant 1, Now I have to do Pickup to Plant 2 .

As per your reply, I hope it is possible but how?

ravi_kumar100
Active Contributor
0 Kudos

Hi,

Kindly refer the below thread.

http://scn.sap.com/thread/1942686

Regards,

Ravi

Former Member
0 Kudos

Hi Ravi,

The given thread is for consignment return but not for consignment pick up.

Here I'm looking for Consignment Pickup to a different plant.

Thanks