on 03-28-2012 5:43 PM
Hi,
I want to configure User Status Profile with follow-up action. My requirement is while I will change the user status as " HOLD" for an Inspection Lot the follow-up action should trigger. Can anyone help me to do the settings?
Regards,
Neel
The UD follow-up action only happens once a UD is made. It can not be triggerred by a change in the user status.
You might be able to use a user exit.
QEVA0010 - Usage Decision check
to trigger off a process of some sort if you want.
FF