Could somebody please give me more insignts into what resources could be called Multi Resources in PPDS? I am aware of some basic types of Multi Resources like:
1. workecenter having more than 1 milling machines will be a multi resource in PPDS etc
But will a furnace with a given volume be a single resource or multi resource. The SCM with APO book by Jörg Thomas Dickersbach mentions this as multi resource as it has a second capacity dimension of volume (so many different products can be processed at one time). But I was not able to understand this example completely. What would be the 1st capacity dimension? Operation time per day? This resource is performing only 1 activity of heating so how would it still be called multi resource.
Any pointers on this will be of great assistance.
Thanks,
DG
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.