Hi All,

Could somebody please give me more insignts into what resources could be called Multi Resources in PPDS? I am aware of some basic types of Multi Resources like:

1. workecenter having more than 1 milling machines will be a multi resource in PPDS etc

But will a furnace with a given volume be a single resource or multi resource. The SCM with APO book by Jörg Thomas Dickersbach mentions this as multi resource as it has a second capacity dimension of volume (so many different products can be processed at one time). But I was not able to understand this example completely. What would be the 1st capacity dimension? Operation time per day? This resource is performing only 1 activity of heating so how would it still be called multi resource.

Any pointers on this will be of great assistance.

Thanks,

DG

Accepted Solutions (0)

Answers (1)

Answers (1)

claire_yang
Contributor
0 Kudos

Hi, I would like to show you one example which shows what is multi resource used in PPDS See attached screenshot.

Regards, Claire