cancel
Showing results for 
Search instead for 
Did you mean: 

ALV reort for budget and actual cost

Former Member
0 Kudos

Hi Experts

Is there any ALV report for budget and actual costs in project system?

thanks

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

PS reports have build using report painter. But by using report output type as 'classic drilldown report' you can export out put thru Excel or pivot (Ex: S_ALR_87013558. 57 etc.,)

Still if it is not suffice you can  customize report.

Regards

Rao

Former Member
0 Kudos

Hi

thanks for help.

Alternatively i believe that i can go for a query.

Please let me know which are appropriate tables to fetch current budget and actual cost and commitements

thanks

ramSiva

Former Member
0 Kudos

Hi Ram

The below mentioned few tables will be useful for your requirement.

COOI - Line items, commitments

COEP - Line items, actuals

BPGE - Budget, overall cost

BPJA - Budget, annual values

PRPS - WBS elements Master data.

Regards

Rao

Answers (1)

Answers (1)

former_member183879
Active Contributor
0 Kudos

Is CJ31, not sufficient?

Former Member
0 Kudos

Hello

CJ31 is just to display budget of one specific project,

Iam looking for a report with ALV.

rgds

ramSiva

Former Member
0 Kudos

There is no ALV reporter(as most of the report are build using report painter) but you can use excel interface to see the report in ALV form.

Regards,

Mahendra Dighe