Status Split in BOP Results

Former Member
0 Kudos

Hello,

What does mean the status Split (Status after BOP) in the BOP Result?

The attached file shows an example.

Thank you.

Januario Faria.

Accepted Solutions (0)

Answers (2)

Answers (2)

michael_thinschmidt
Contributor
0 Kudos

Hi,

I suppose you have activated the check on schedule line level for BM - Sales order documents.

Check in transaction "S_AP9_86000161" your settings and read the SAP help on this:

http://help.sap.com/saphelp_scm70/helpdata/en/45/9b68d07cb652f5e10000000a1553f7/content.htm

Thus the BOP is not checking at order item level ! BOP checks at schedule line level and thats why you have the "split" in the BOP result screen.

Hope this helps.

best regards,

Michael

Former Member
0 Kudos

Hello,

Here, the system splits up an existing BOP variant into variants that you can schedule as batch jobs that are independent of each other. You can start these either simultaneously or at different times.

The concept is named as Parallelization for Variant Split.

You can view more details in the below link:

http://help.sap.com/saphelp_em70/helpdata/en/45/ef349fc4ae04a7e10000000a114a6b/content.htm

Hope the information was useful.