PO Acknowledgement not flowing to EM from ECC when it is received via EDI

Former Member
0 Kudos

Hi Experts

Hope you might have faced this situation already. Around 90% of PO Acknowledgements come through EDI and update ECC (Idoc Message Type ORDRSP). But this is not flowing to EM. Which ever are created manually are flowing to EM.

We made change referring one of the notes

 

The Include LEINMTOP requires below correction:

Replace the following line of source code

DATA: call_em_flag VALUE ' '

with

DATA: call_em_flag VALUE 'X'.

After this change also, the required parameters are not getting filled including EKPO and EKES tables. So ECC is not able to send event message when AB acknowledgment has creation indicator 3 (EDI).

I approached SAP and they replied saying that it is not possible with standard SAP and it requires redesign of ORDRSP Idoc programs.

Please guide me how to resolve this problem.

Best Regards

Ravi

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Experts

Your quick response to this is very much appreciated.

Best Regards