CS02-Change BOM Screen exit/enhancement for Change Management

Former Member
0 Kudos

Dear Experts,

How to  make the Change Number field in CS02  initial screen mandatory for selective plant/plants only. e.g. In CS02, If we enter XYZ plant in the Plant field, automatically Change Number field will get mandatory.

Without Change Number, user won't be able to make any changes in the BOM for selective plant/plants.

Please suggest the solution for the same. Thanks in advance.

--

Kind Regards;

TRB

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check the thread below.

http://scn.sap.com/thread/1391287

Regards.

Former Member
0 Kudos

Thanks for the response.

I have already checked those links, which is not a solution for our requirement.

We don't want to make Change Number field mandatory for CS02 Screen. We want to have it mandatory only for specific plant, not for all plants.

I hope you got the requirement. Please let us know, if this can be done by any mean in SAP.

Awaiting for your valuable response.

--

Kind Regards;

TRB

Former Member
0 Kudos

Hi,

You can distinguish this behaviour across the plants by means of aurhorization management.

Create two roles where C_STUE_WRK grands authorization only for required plants. In one of the roles include C_STUE_NOH in which you do not want EC orders to be mandatory.

Regards.

Former Member
0 Kudos

Thanks for the response.

We did it by Screen validation.

--

Kind Regards;

TRB

Former Member
0 Kudos

Thanks for the response.

We did it by Screen validation.

--

Kind Regards;

TRB

Former Member
0 Kudos

Thanks for the response.

We did it by Screen validation.

--