on 03-22-2012 9:12 AM
Hi,
For my putaway process using storage control, I am find that handling units are missing in inbound delivery document. Any suggestion to find the missing link will help.
I did the the following steps
1- Create PO
2- Create inbound delivery with packing activity.
3-Check inbound delivery request and handling unit available.
4- Create inbound delivery document and I see that handling unit is missing.
I checked all the settings and looks ok with process type 1011 and warehouse door determination. I hope this helps.
Any help is much appreciated.
Thanks and regards,
Bhaskar Mandal
Hi Bhaskar,
This is most odd, normally the HU dissapears from the ID after it is putaway in the final bin. Please check in it is trully the 1011 (check the position in the ID that it has the 1011 process type allocated) and if so what external steps you have allocated for the POSC. Also, check if your product is relevant for process control (Proc.Type Det. Ind. with 01 in the product master in the Whse Data tab).
Also, you can check that the ID has not the Warehouse Activity completed status, if so, what I said at the beggining applies with the deletion of HU from ID after putaway.
All the best,
Claudiu Maxim
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.