403102 - Offset takes non-working time of resource into account (OSS notes)

Former Member
0 Kudos

Hello Friends,

I have implemented the OSS notes 403102 for considering the offset value without considerding the non working time of the resource.

but as i have implemented the sample code given there(copy & Paste) the functionality seems to be not working.

the productive hours maintained in the transaction /SAPAPO/RES01 is 8.5 hrs.

previously the system was considering the productive hours as 24 and was calculating.

after implementation of the notes if I specify a 4 days offset iam getting 3.5 days offset . for 6 days its 5 days offset.

does anyone faced this issue.

Any help will be highly appreciated.

if u any code modification u can mail to me at mahadev.shetty@tcs.com

Thanx & Regards,

Mahadev Shetty.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

thanx got the solution thru config change