No schedule lines due for delivery up to the selected date

Former Member
0 Kudos

Sap Specialist,

Again I have met the following Error in Outbound Delievery.

<u> <b>No schedule lines due for delivery up to the selected date</b></u>

In Sales Order the Req.Deleivery Date is 24.10.2006. But in Schedules Line.

<b>Date</b> <b>Qty</b>

31.08.2006 - 10800

30.09.2006 - 10000

31.10.2006 - 12000

30.11.2006 - 500

31.12.2006 - 5000

31.01.2007 - 1200

28.02.2007 - 39700

31.03.2007 - 10020

Which date I have to put the selection Date in 'VL01N'.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member396676
Contributor
0 Kudos

HI,

In each case,pl check confirmed delivery date in sale order.Put that date as selection date in VL01N.

thanks,

Vrajesh

Former Member
0 Kudos

i had met the same problem。

thank U for the answer,that help me a lot。

rmazzali
Active Contributor
0 Kudos

try with 31.03.2007 and you will deliver all the item quantity IF there is material available !!!

Roberto

Former Member
0 Kudos

Hi,

It says that for the requested delivery date you dont have the required item qunatities confirmed with a schedule line. Either you need to wait till the schedule line date is due in the system or give the suggested schedule line date in VL01N and execute the delivery. You would be able to do it. Make sure you would be getting the required stock into unrestricted by that time.

This should fix the issue. Pl reward if helpful.

Thanks & Regards

Sadhu Kishore