on 03-16-2012 10:01 AM
Hello All,
I want to setup the system so that System does not allow project release till Budgeting is done?
And i am trying to achieve this via user status and here is what i did:
I created a status without status number --> In transaction control i selected Budgeting (Forbidden and next action set) AND selected RELEASE (with Influence ALLOWED and next action No Action)... but with this even after i do budgeting system does not allow Project Release??
Any suggestions on how can this functionality be achieved?
Thank you.
Regards,
Jatinder
Hi Jatinder,
Create a default user status which will forbid release and get RESET on Budgetting.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shrikant,
I acheved the desired function partially with the following:
Create a user status profile for WBS say 'Check'
Status Number : 1; Status ID: RelN; Initial Status: Yes; Lowest: 1; Highest: 2
Business Transaction: Release - Forbidden & Next action 'No Action'
Status Number : 2; Status ID: BudG; Lowest: 2; Highest: 2;
Business Transaction: Budget - No Influence & Next Action Set
Business Transaction: Release - Allowed & Next Action Set
With this system stops release before budgeting, but even after budgeting system alows me to release only WBS elements and not Project def (PD), i have to manually change uder status from PD; any suggestion to also automatically reset user status for PD once budgeting is done??
Regards,
Jatinder Bansal
Hi,
I think you should be using only 1 user status to achieve both. As stated in earlier reply, the status will block release and once budgetting is done it will be RESET automatically. In transaction control we can also reset user status as we set it based on business transaction.
Regards
Shrikant
Dear Shrikant,
I have already tried following as well:
Created one user status with initial status flag set; then i maintained following:
Business Transaction: Budget - Forbidden & Next Action Set
Business Transaction: Release - Allowed & Next Action Set
Now system does not even stop release?
Can you please share some more details on how to setup this scenario.
Thank you.
Regards,
Jatinder