Committed cost in PR only after release

former_member513364
Participant
0 Kudos

Hi Experts,

Is there any control to have the committed cost getting released only after PR/PO release.ie once PR is created and saved, I have the commitment cash flow. I need to have the cash flow only upon release of PR/PO. Can anyone explain how to go about for the requirement. Thanks.

Regards,

Murthy

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member209919
Active Contributor
0 Kudos

Hi Murthy,

I think this is not possible, PR/PO status is independent of the controlling document that it is the responsible to create the commitment, ( obviously except the delete status).

You cannot get this by settings and really I am not sure how to achieve this by develop.

Sorry,

Sara