Hi Gurus,

I have a sales order in which Schedule line for one Line item is not confirmed(because there is no stock for the same material).

But it is showing in MD04.. ??? How Is this Possible..

can anybody let me know about this .. how to make system not to include that material into MD04

Thanks

Rajanish

Accepted Solutions (1)

Accepted Solutions (1)

Shiva_Ram
Active Contributor
0 Kudos

Run program SDRQCR21 in SA38 for that material and check again.

P.S: You can very well search the forum with key word MD04 discrepancies, then you can find solutions.

Regards,

Answers (2)

Answers (2)

former_member217082
Active Contributor
0 Kudos

Hi Rajanish

Check the plant parameters,and also check is what is the MRP Parameters of that plant.So you have to take your MM Consultant help in this issue.

Regards

Srinath

former_member223981
Active Contributor
0 Kudos

It is correct for the system to show a requirement in MD04 in this case. A requirement exists regardless of the confirmed availability of the material. If you want to remove this requirement, you can set the reason for rejection in the item