on 03-14-2012 5:29 PM
Hello
Is there any option to use CCPM methodology created by Mr. Goldratt in SAP PS?
What about transfer network form CPM methodology to CCPM in PS?
Any one use it?
Hi,
I am not sure of using to an extent in PS and never come across such kind of requirements in my experience.
Let others speak their experiences.
Regards,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Sudhakar
Thank you for your answer. CCPM methodology is very young, maybe since 1997 as I remember, so not every one hear about it But some customers would like to use it.
I think I have an idea about it. Probably I will write some blog post about it.
Hi,
we have realized in 2013 the CCPM basic features based on SAP PS, SAP Progress Tracking and our ABAP WebDynpro Add Ons. After intensive discussions with CCPM specialists and our customers, we designed our first version with a static determination of the critical path. This could be enhanced to a dynamic determination via capacity load and status information of the relevant Network activities. The degree of processing and grade of the buffer consumption will be processed within one buffer activity.
Features:
Hi Steffen
We have this requirement in our project. Iam trying to understand how this can be implemented using Network activities.
How can we get the aggressive timeline and buffer timeline in the activity?
The way i understand you, we need to create 2 activities for each activity task - one for aggressive time and one for the buffer.
How do you maintain the relationships for these buffer activities?
Anjaneya
Hi Anjaneya,
to realize the aggressive timeline and buffer timeline we use basic dates and forecast dates. You need no further activities, only for the buffer we use one additional activitiy. The buffer activitiy will be followed by one activity with a constraint date. We use Start/ End relationships.
Steffen
Thank you Steffen for the reply.
Can you please provide some insights of how the basic dates and forecast dates canbe used to realise the timelines as in CCPM.
Assuming that we write a code to calculate the % Completion & % Buffer utilisation, how would we get the scatter plot in ECC?
Anjaneya
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.