General cost activity in project

Former Member
0 Kudos

Hello All,

              As i am creating general cost activity in cj20n for some cost ,and some less amount i am  posting into FBCJ . So what is the benefit of creating this activity and how can we see this actual cost posted in petty cash and left amount for activity.

regards

Manisha

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

General Costs activity is usually created when you are not sure about the nature of expenditure that is going to be incurred on a project. These can be anything from travel expenses,Insurance costs, Medical expenses etc.,

I am not sure why you are using FBCJ for posting. There are other ways of posting an actual cost on the project. Once actual costs are posted on these activities it can be seen in the report CJI3 or for that matter in most of the standard PS reports.

Former Member
0 Kudos

Thanks

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

correct Gokul

these are activities which are not usually confirmed

you would raise a po against these and post costs via goods receipt etc