Hi Experts

I was try to learn the concept of sample drawing procudure as i go i was trapped with an error while i try to create a inpection lot .the error is:"

Samp. determination: Data missing for no. of containers and lot container

Message no. QY307"

So please tell me what are the master  data  required as prerequistee to work with sample drawing procdure

Expecting a details tips on the issue

Abu Fathima

Accepted Solutions (1)

Accepted Solutions (1)

anand_rao3
Active Contributor
0 Kudos

Hi Abu,

You must be using sample drawing procedure (at header of inspection plan) that contains “Consider no. of containers” checkbox ticked.

  1. Either you remove this tick in QPV2 (if you don’t want lot containers to be entered)
  2. Or mention number of lot containers at the time of lot creation. (If the inspection lot is already created, then go to QA02 and in samples tab mention No. Containers.

Regards,

Anand Rao

former_member223028
Participant
0 Kudos

Hi Rao

Thanks for the answer

As i removed tick mark for consider no of container i got another error as follows

Sample determination: No sample drawing item found

Message no. QY304

1.And aslo in the header of the inspection plan what is the inspection point need to assign (i assign 200)

2.And in sample drawing procedure uner the inspection point tab i select sample managment..is it the correct one

Regards

Abu Fathima

Former Member
0 Kudos

Hi Abu,

When you are using sample drawing procedure :

1.You have to assign Inspection point related to sample management in task list header.

2. You have to assign the sampling procedure relevant to inspection point to "all" the MIC's

Once you make sure this just remember to  remove container data in SDP and make sure that you have entered data in either of the "primary sample" AND/OR "pooled sample" AND reserve sample.

Answers (2)

Answers (2)

Former Member
0 Kudos

hi,

U need to check the no. of container size field, secondly check ur sampling procedure and its valuation type, inspection point in quality plan and assignment of sampling procedures in MIC's. if u don't want a fixed no. of containers size  then remove the size from QPV2 and use the sampling scheme for auto sample size calculation.

Former Member
0 Kudos

Hi,

1.You have to assign sampling proceduure to each MIC in the task list.

2.Assign the container data in the sample drawing procedure.

Please go through the below links for more details

http://scn.sap.com/thread/497054

http://help.sap.com/saphelp_40b/helpdata/en/2d/35208b448c11d189420000e829fbbd/frameset.htm

http://help.sap.com/printdocu/core/print46c/en/data/pdf/QMIMSM/QMIMSM.pdf

Regards

Hari