on 03-13-2012 12:38 PM
Hi,
I have planned project cost through CJ40, when i am confirming an activity and running RA(KKA2) the actual cost of activity is getting added to plan cost of the project. I checked other reports also where i found that neither plan cost of activity nor its actual cost is added to WBSE plan cost. I wonder why it is happening in KKA2 results only. I have used "Object indicator for order value" to restrict the addition of network cost to WBSE cost.
Please suggest..
still looking for a solution.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Could you check in OKG3 transaction your settings ? select your controlling area --> Ra key of the WBS --> Status of the WBS --> check settings in Planned values if they are according to your result,
Regards,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.