Dear Experts,
we have combination of Fund center xxx and commitment item yyy, which is checking budget and also we have one more combination Fund center zzz and commitment item yyy, but system is not check budget.
In funds management where we activate this settings, we are on 4.7 version using former budgeting. Thanks.
Regards,
Raj
03-13-2012 1:32 PM
03-14-2012 2:05 AM
Hi Aleksey,
Thanks, I have tried but no Luck, any other T.code to check.
Regards,
Raj
03-14-2012 4:12 PM
03-15-2012 11:13 AM
Hi,
In what circumstances you discover that there is nobudget check? Are you trying to modify the existing budget or consume it? Also, try reconstructing AVC ledger (FM9P, FM9Q) and see if the problem is solved.
Regards,
Eli
P.S. When you say that you checked OF23, suggested by Alexey, does it mean that you have no definitions there at all or you suppose that the strategy defined there should not make an exception for this combination?