on 02-07-2007 7:01 AM
Hi SD Experts
can u say me the clear difference between Scheduling lines and Delivery schedule.
where we will maintain deliver schedule. whether delivery schedule is automatically created along scheduling agreements..
with regards
James
Hi,
Go through this
<u>http://help.sap.com/bp_biv335/BI_EN/html/BW/SchedulingAgreementsAnal.htm</u>
Mohan
Award points if it helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Delivery Schedule : The delivery schedule contains information on delivery quantities and dates. A new delivery schedule replaces, in part or completely, the previous delivery schedule with regard to date and quantity.In the more general context of outline agreements, delivery schedules may be referred to as scheduling agreement releases.It is a document sent by Electronic Data Interchange (EDI) or fax to the component supplier to release a quantity of the material or materials outlined in the scheduling agreement.
Schedule lines : Are used by the system to determine if the item is relevent for delivery.Only those items that have schedule lines assigned will have a delivery created for them.The deliveries are created for the dates and quantities assigned to the respective schedule lines.
reward me if i am clear.
regards
kiran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi James,
Schedule Lines: Has basically information realted to delivery scheduling in Sales Order level.
Delivery Scheduling: Is a process using which system will determine what are the different activities which need to be performed and time taken for each activitiy only after which the material can be delivered to the customer.
Delievry scheduling will be started only from the material availability date i.e., system will first determine the material avail date and then do scheduling. By default Standard SAP system does Backward Scheduling in case material availability falls beyond the required delivery date system will do forward schedluing
Delivery Scheduling consists of the following Basic activities:
We give deatils while creating order:
Order Creation Date
Required Delivery Date
Order date - Material availability date - Transportation Planning Date - Loading date - Goods Issue Date - Required Delivery Date
Time Between GI Date and required Delivery Date is called Transit Time
Time Between LoadingDate and GI Date is called Loading time
Time Between Material Availability Date and Loading Date consists of 2 components - Pick / PackTime and Transportation Planning Time
System has to calculate all this before it determines the confirmed delivery date.
Give your mail Id I have some Presentation I will send you across.
REWARD POINTS IF IT HELPS
Regards
Srini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
<b>Schedulelines</b> the syatem allow delivered quantity and the delivery date.
<b>Delivery schedule</b> -physically stock available from stroage location
rewards point it helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Schedulelines gives the information regarding delivered quantity and the delivery date.
Mohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.