MD04 with SO dsplay availabitty

Former Member
0 Kudos

HI

Today i raised a SO for Cat no 1114057 for 50 qty item is confirmed on 12th Feb 2007 (MAD as 12th Feb 2007).Hence two shedule lines were displayed in SO.

One for today 5th Feb and then for 12th Feb.

And then after selecting Disply availabiltiy system takes me into MD04 and its showing for 12th Feb Date Recvd qty as -52 and confirmed qty as -52.

If i goto MD04 seperately after giving mat no plant details system is now showing for this order for 5th Feb recvd qty as -52 not confirmed qty and also its not showing any values for 12th Feb.

Why in MD04 i am able to view 12th Feb details waht i am able to view it via SO?

any guesses pl .

Reg

Shankar1242

Accepted Solutions (1)

Accepted Solutions (1)

rmazzali
Active Contributor
0 Kudos

First of all make sure you are using the same plant in SO and MD04.

Then make sure you have saved the order and refreshed MD04.

If you goto requirements simulation in the sales order you get only a simulation and not a real requirements: to see them in MD04 you have to save the order before jumping to MD04.

Also you can run report SDRQCR21 to check and restore missing requirements.

pls. reward if helpful

Regards

Roberto