MRP view maintenance for Material Master

Former Member
0 Kudos

What is the basic entry for R3 material master, if, I want EBP below condition works:

Stock in R/3 sufficient: Shopping Carts creates MatReservation.

Stock in R/3 not sufficient: Shopping Cart still creates MatReservation, and when run MRP (in R/3), it gives Purchase Requisition, with the exact shortage qty.

Info: We have set customizing in EBP so that every follow-on document for Shopping Cart will be Reservation.

-Mimi-

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

In R/3 , the material should have MRP view and all planning related settings ...

wr u want to go for consumption based planning or deterministic planning .

Based on the planning procedure setting in MRP views of the R/3 sytem , PRs will get generated.

This is what u are looking for .. otherwise post your feedback...

Regards

Mani

Former Member
0 Kudos

Hi,

You can use the foll BADI's

BBP_TARGET_OBJECTS

BBP_TARGET_OBJTYPE

BR,

Disha.