Hi Friends,
I have been looking for a solution for "how to maintain relationships among activities of two different projects", but not able to find out the solution.
Can any one tell me is there any work around two maintain relationships among activities of differenct projects.
points can be alloted for suitable solution.
Thanks in advance and looking forward to have your valuable suggestions.
Regards
Sudhakar
Dear Sudhakar,
Good morning and greetings.
Solution is very simple actually. You can maintain relationship for 2 different project same way as you maintain within the project activity.
Select WBS- select Network- Select Activity which you want to maintain relationship with other Project.
Select relationship button Chain Symbol
Enter activity no e.g. 0010 and enter the Network no of other project also maintain relationship type
e.g.
SS relationship (Start - Start)
FF relationship (Finish - Finish)
SF relationship (Start - Finish)
FS relationship (Finish - Start)
System will make a link and dependency of two activities of two different project.
Enjoy SAP .
Dont forget to give points if its useful ans.
Namskar,
Ketan Dave
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.