on 01-26-2007 5:36 PM
I want the field PRPS-MATNR to appear on the WBS.Can I use SFAW to add
to the PRPS module pool? Does it impact future upgrades? also if this
is included as a modifiable field then which layout screen will this
appear? How can I update table V_PRPMM
Regards
Virendra
Virendra,
The material number PRPS-MATNR is only filled if the project is a production lot (created over the transaction MDL1).
Is this your case?
Due to the number of fields used in PS system, not all have been made
eligible for field selection in the standard system. It is however usually possible to extend the list of the modifiable fields of the field selection in Transaction SFAW as long as the fields are relative to tables PRPS or PROJ.
Hope this helps!
Rgds
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Virendra
You can introduce fields in transaction SFAW into the field selection
procedure. But this is considered a modification due to the implications
of note 114390. Therefore if will be affected during the upgrades.
Have you considered CNEX0007? It may be useful for you in this case.
Rgds
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This the link of PP to PS. If you have created a Production order for a material, and you have linked the WBS in same order account assignment, in that case PRPS-MATNR as a display you can see the linked material from same.
Enjoy SAP .
Dont forget to give point if useful ans.
Namskar,
Ketan Dave