on 12-28-2006 3:36 PM
Hello,
Please, can anyone explain the integration points between PM and MM/FICO during the PM configuration.
Thank you very much.
Below are some integration aspects:
Integration with MM:
1.Material master record for Batch Managed material as Equipment
2.Reservations and Goods Issue for Maintenance Order
3.Material valuation class/types for refurbishment materials as equipment
4.Triggering PR from Maintenance Order
Integration with FICO:
1.Asset/Sub-Asset numbering in Equipment Master Data
2.Activity based costing for Operations performed through Maintenance Order
3.Settlement of accrued costs in Maintenance Order to G/L Account,Cost Center,
Asset etc.,
Note: Above is not an exhaustive list.
Regards
Udayakanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.