cProjects 4.0 - HCM 4.7 Integration

former_member189058
Active Contributor
0 Kudos

Dear all,

I need to integrate SAP HCM 4.7 to cProjects 4.0

I have followed the configuration guide and the following notes:

550055; 677924; 363187

I get to see all the qualifications, jobs, positions, organization units created perfectly in cProjects. Even the Org unit assignments are perfect.

However, Persons of HCM cannot be seen as Business Partners. Infact Org units can be seen as business partners under the org unit role.

Pl. guide me through a solution for this.

My business scenario requires me to have HR persons in cProjects with their qualifications and time specifications from HR, so that the resource planner in cProjects can search for resources based on qual n time.

I have also installed WFM 2.0 add on.

Pl. guide me through the customizations of WFM (a guide for that if available).

Regards,

Reema.

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member189058
Active Contributor
0 Kudos

Solved

former_member189058
Active Contributor
0 Kudos

Solved

Former Member
0 Kudos

Hi,

Please also check data maintained at

1. SPRO-- Cross application -


 SAP Business partner --- External Data transfer.

2. Also check at front end master data T-Code ‘BP’