on 12-19-2006 10:29 PM
Hi,
I am getting the source Date field as 'Text' type and want to convert it to Date type.
Is it possible in import Manager?
What are the best way to manage the issue.
Appreciate your reply
regards,
reo
Hi Reo,
The data types of source data values are automatically
converted within the Source Values grid based on the data type of the
destination field to which the source field is mapped, even when stored
in the source data as text values.
Original source values appear with their original data type in the Value
column, and the converted values appear in the Converted Value
column with the data type of the mapped destination field and the
proper grid cell type for editing (e.g. text, numeric, measurement,
currency, date, time, Boolean).<i> If necessary, individual values can then
be manually edited to override errors or omissions in the source data.</i>
Regards
Neethu Joy.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Initially you have to map the two fields at source and destination side,then you will have to manually do the value mapping for destination field .
I hope this will help you.
Regards
Nisha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi reo,
I think u have not manually converted the date values before importing. You need to convert the text field into destination literal date in the bottom pane after mapping it and before importing.
Thanks,
Minaz
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Reo,
You define to destination field as Date Type then you can map the field
Source (type:text) to destination (type:date).
In the import manager you determine your date import formate in the import Configuration window e.g YYYMMDD or DDMMYYYY etc
You can then convert to text by right clicking on the source field and converting to Original Value
Hope this helps
Con
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Con,
Can you please elaborate bit more .
My destination field is already defined as Date but when I am trying to map the text date field(source) to destination Date type field , the "map" function is NOT getting enabled.
I think I missed to give these details in my last mail.
I am sure you can give some detail insight to it.
Thanks in advance
-reo
Configuration Options affect the behavior of MDM Import Manager.
You can use Options command in the main menu to open the Configuration Options.
You will see a category called Dates.
This option allows you to specify the format of the incoming date values.
Choose the Date format of the incoming dates
It can be one of the following
YYYYMMDD
MM/DD/YYYY
DD.MM.YYYY
After setting this option, try mapping the source and destination fields.
Hope this helps.
User | Count |
---|---|
89 | |
10 | |
9 | |
9 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.