on 12-14-2006 9:15 AM
Hi,
Out client is going to upgrade R/3 4.7 to ECC 6.0, and SRM 2.0 (BPM 3.5) to SRM 5. I think R/3 4.7 to ECC 6.0 is fine. But I have doubt about SRM 2.0 to SRM 5 upgrade compatibility. I could not able to find any document or OSS notes. If any idea, please let me know.
Thanks in advance
Regards
Srinivas
Hi,
here the upgrade paths to SRM 5.0:
Upgrade to SAP SRM 5.0 is possible from:
SAP BBP 2.0B (SAP EBP 1.0); SAP BBP 2.0C (SAP EBP 2.0); SAP EBP 3.0; SAP SRM 2.0 (WITH SAP EBP 3.5); SAP SRM 3.0 (WITH SAP EBP 4.0); SAP SRM 4.0
Regards
Dennis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
we already upgrade the classic scenario - self service procurement - version EBP3.5 to SRM Server5.5 (SRM 5.0). One tip you should be aware of the release notes to SRM 4.0, because the biggest changes are to this release. Upgrade compatibility is no problem. The project runs very smooth.
regards
Armin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello. I noticed your reply to another user about the upgrade to SRM 5 and it sparked a question from me..... how did you size the upgrade?
This is my first time working on an upgrade and I've been to the Marketplace, I've looked at the upgrade master guides, everything says to use the Quick Sizing tool..... UNFORTUNATELY they do not provide any details on HOW to use the Quick Sizer or if there are reports we can run to answer the basic questions like the #'s of transactions in our current system? # of transactions by user? etc...?
Please, if you're able, send details to angela.bilkey@anheuser-busch.com, it'll be a tremendous help.
Thanks so much.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.