Function element value in ARTMAS IDoc

Former Member
0 Kudos

Hi,

My scenario is IDoc->Xi->File, my mapping is based on Function element (if the IDoc contains changes or new data) but all time I got just 005 as Function witch mean new article.

Is there any set up to do in order to get 004 for changes and 005 for new data?

Thank you,

Accepted Solutions (0)

Answers (1)

Answers (1)

bhavesh_kantilal
Active Contributor
0 Kudos

Hi,

Your functional team should be able to help you in this. The report that generates the Idoc needs to be changed and this is handled by the functional team.

Regards,

Bhavesh

Former Member
0 Kudos

Thanks lot for your answer.

Please can you detail litle bit youor answer, I mean witch kind of configuration I should check?

Regards,

Fouad,

bhavesh_kantilal
Active Contributor
0 Kudos

Hi,

You are doing an Idoc to File and the idoc is sent from your SAP system.

In real time, the functional team would have scheduled a report that will create the idoc and send it to XI. The Logic for creating the idoc would be with your functional team. So,. it would be best to ask the functional team for the clarification on this and ask them to send the appropriate data.

Regards,