on 12-05-2006 8:26 PM
Hello Friends,
I am working on classic scenario, where once the SC status changed as approved , I have to create multiple PO from that single SC based on vendor number in R/3..
Please help me out for this ..
Thanks,
John.
thanks,
John.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello, PO grouping is made on these fields
- vendor
- contract number
- purchasing organization
- purchasing group
- backend document type
- company code
- time frame, from ( for limit items )
- time frame, to ( for limit items )
Hope this helps
Regards, Luciano.