Hi all,

When I make change in BMP design object and activate it, should update the config side to? how?

Thank you,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

To be sure that u have the latest one in config, Delete the Business process in Directory. It will issue a warning ignore that warning. Recreate the Business process once again with the same name that was used before. Activate the changelist.This work around will make sure that u have the latest version in configuration.

Regards,

Sudharshan

Former Member
0 Kudos

Thanks for your answer,

Still want to know the standard way to keep config object updated!(delete the Config is not a safe way)

Thanks lot

bhavesh_kantilal
Active Contributor
0 Kudos

Hi,

The object are updated automatically.

When you make a change in your BPM in the IR and activate the same, the change is reflect in ID as well.

Just like Interface Mapping changes will get reflected, Integration process Changes are also reflected. No manual work needs to be done ( except for activation though! )

Regards,

Bhavesh

Answers (1)

Answers (1)

bhavesh_kantilal
Active Contributor
0 Kudos

Hi,

After creating and activating your BPM / Integration process in IR, you should import the same in your Integration Directory.

Right Click on Integration Process in your Config Scneario and then new and select your BPM.

Take a look at this blog for a simple BPM,

/people/krishna.moorthyp/blog/2005/06/09/walkthrough-with-bpm

Regards,

Bhavesh