on 11-26-2006 12:28 PM
Hi experts,
Have anyone of you some ideas how to creating a object link to another phase in another project? Are there possibilites for enhancing the the type of objects link via a BAPI or something in cProjects 4.0?
Thanks, Camilla
Hi Camella,
You can try this in IMG activity
"Make Settings for the Linked SAP Objects". But you need to try copy an existing entry and change relevant tables parameters
I have done this for R/3 Transaction in cProjects 4.0 + ECC 6.0 and Iam sure it will work for Project Phase also
Pls,let me know the version you are trying this feature
regards,
Ramakrishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi all,
I don't think that just copying customizing will work. You will need to create a new object link type (development). When you go to the SAP Support Portal -> Installation and Upgrade Guides -> mySAP Business Suite Applications -> mySAP PLM -> using cProjects Suite 2.0, you will find a guide.
Best regards,
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
6 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.