Transfering external requirements to SRM on plant level, PD procument

Former Member
0 Kudos

Hi all

I'm working for a costumer right now, where we have implemented Plan Driven Procurement. We are running BBP_EXTREQ_TRANSFER in order to transfer the requisitions to SRM. The Costumer wants to control what requisitions that are transferred i.e. based on e.g. MRP controller, plant - but the program doesn't offer these variants.

Does anyone has any suggestions on how to solve this? Other than making a Z program ;o)

Best regards Maria

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Maria,

All external requirements are hold to transfer in EPRTRANS table on backend side.

If You want you may to implement Z program to control these req's.

Regards,

Marcin Gajewski

Former Member
0 Kudos

Hi all, if you clear CH_EPROFILE in customer exit BBPK0001 the external requirement is not written in table EPRTRANS so you can control what are the requirements that have to be processed externally.

Regards, Luciano.

Former Member
0 Kudos

Hello, in R/3 customer exit BBPK0001 can be used to determine the external procurement profile .