on 11-24-2006 12:26 PM
I have one question.
Is it posible to create a PO directly in MM(R/3) and then send it to SRM?. Is It mandatory that the PO was created for a purchase requisition or quotation from SRM?
Somebody sayd me that there is not an "escenario" where I create an MM PO from a MM purchase Requisition and i could see it in SRM.
sorry about my english
best regards
Hi Jordi,
In standard, you can send a R/3 purchase requisition to SRM.
However you cannot send a R/3 PO to create a SRM PO except if you manage the whole process in specific development.
Kind regards,
Yann