Hi,
I am trying to create PO from Sourcing. After the bid is accepted I am trying to convert it to PO. But it is creating 2 PO in R/3. Please let me know how to solve this?
Regards,
Chary
Hi Chary,
PO split occurs especially when :
ship to location, address or vendor are different in one of the line item.
Could you please check waht data is different in your 2 PO ?
Kind regards,
Yann
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello, PO grouping is made on these fields
- vendor
- contract number
- purchasing organization
- purchasing group
- backend document type
- company code
- time frame, from ( for limit items )
- time frame, to ( for limit items )
Regards, Luciano.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mani,
Thanks for the reply.
I want to see the details in a standalone scenario for the PO created in the EBP and not in MM.
Here I found Header data ---> Basic data ---> only Purchasing org and purchasing group is displayed for the PO created but no company code tab.
I have more than one Co.Code and want to create a direct PO without reference to SC for which where to select the respective Co.Codes.
Sridhar.
Hello,
Here you can find technically..
1. Goto the tcode BBP_PD.
2. click on the link ---> Details which is under the HEADER information.
3. In the table section BBP_PDHGP , you can find the company code info.
I think we can't see the company code info on the screen and it will defaults the cocode info from the org structure .
Now coming to the PO split it may be because of the purchasing org or due to any other criteria mentioned by Luciano.
Regards,
Mani