cancel
Showing results for 
Search instead for 
Did you mean: 

No cost center could be determined for organizational unit 00000000

Former Member
0 Kudos

Hi experts,

I came across this error while carrying out the Calculate costs function.

Please help me in this regard.

thanks in advance

Anand Bende.

Accepted Solutions (0)

Answers (4)

Answers (4)

schneidertho
Advisor
Advisor
0 Kudos

hi anand,

honestly speaking i am not completely sure. since the internal order has been created, i assume the problem must be in the cost calculation.

there the organizational unit is used to determine the rate to be used for the calculation

a) either the cost per unit, which you have maintained in cProjects

b) or the costs according to the cost center / activity type combination

furthermore it should also be used to get the cost center which is credited in cost center accounting

therefore i think you need to focus on that. e.g. something in the cost rate customizing might not be ok. or maybe the system cannot get the cost center from the organizational unit in HR. did you maintain one there?

hope the information helps you.

best regards

thorsten

schneidertho
Advisor
Advisor
0 Kudos

Hi,

a) has the internal order been created? Please check in R/3.

b) Have you maintained an organizational unit in the cProject?

c) Have you defined cost/revenue rates in customizing?

BR

Thorsten

Former Member
0 Kudos

hi thorston

i have checked al the entries tht you have told, all are made. cna u focus on why this is happening?

thanks in advance

anand bende

Former Member
0 Kudos

Hi!

Did you find a solution for this error message?

Thanks a lot!

Kind regards,

Isa

Former Member
0 Kudos

Hi,

1. you try giving the organization until as you find in the InternalOrder.

2. You try assiging the project type & project profile numbers correctly.

3. clear all the invalid queue items in SMQ1 and SMQ2

hope these will help.

regards,

boobalan

Former Member
0 Kudos

There is missing cost ctr in your work order. or no cost ctr assigned tour your technical object. Please check

Former Member
0 Kudos

hi ketan,

we are using cprojects 3.1, we have already assigned cost center in internal order.

where we have to assign the cost center again, can u elaborate on this matter.

in brief we have created a small project with resource assignment and the internal order CPR1 which includes the req cost centre and resp cost centre. While calculate cost tab is activated the messages log contains this error.

Please help in this regard

thanks in advance

Anand

former_member189058
Active Contributor
0 Kudos

Hi,

Refer OSS Note : 875275

Regards,

Reema.

Former Member
0 Kudos

hi reema

thanks for ur help

i have gone through OSS note 875275 and also made the correction but the same error is still coming.

i am also trying some other method.

thanks if you can flash more light on it.

thanks

anand bende