on 11-01-2006 4:36 PM
Hi,
We use R/3 PS for managing projects. We use CJ20N to create and maintain project plans. In the header of the project (section dates), there is a field called 'Factory Calendar'. The start and finish dates on this screen come from the factory calendar that you pick. However, when you go to an Activity -> tab 'person assignment' and do a drop down on column 'Date', it doesnot pick the factory calendar that was selected in the header. As a result, we don't see any of the holidays defined etc. The question is, which calendar is used on this screen? Is it possible to assign the factory calendar for this screen as well?
If somebody has any info and can share, I would appreciate it.
Thanks
Nirmal
This flows through Work Centre Capacity data. Please go to work centre which is being used in the activity. Go to Capacities Tab double click on capacity category and check assigned calendar in Available Capacity box.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.