In transit quantity doesn't show up after PGI

Former Member
0 Kudos

Hi,

This is for VMI scenario where customer demand is converted to

internal DC to create Stock Transport Order. After the TLB order data

(STO) is CIFed to R/3, which is CIFed back to APO. After that I created

delivery and it also successfully CIFed to APO. But when I PGI the

material from shipping point, the quantity should show up in IN TRANSIT key figure in SNP planning book which doesn't.

Can anybody throw light on this?

Thanks,

San

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I hope by this time you must have resolve this issue