on 10-12-2006 6:55 PM
Our Basis team is trying to install the IPC. All the steps in the setup guide have been followed until initial data-upload per the installation guide. We defined an R/3 system and a local database.
When the download is initiated or even the connection is tested, the connection fails with a R/3 terminating with a short dump in the CRM_SEND_DATA function module. Has anyone made faced this issue?
First of all when there is no material master does the IPC have to connect to the R/3?
Hello Robert,
Can you let us know what the error message or the dump you are getting. So, that we can try to let you know the exact solution.
Regards,
Mani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mani,
The error message being generated by an abend message is "Connections to IPC not possible!". There is a note 846021 which give the solution for the problem but i did not see the blocksize it talks about. Also, even if I test the connection and don't actually try to download any data, the shortdump occurs.
Also would be grateful if you can give some information on the relevance of IPC.
Thanks in advance!
Regards,
Robert G.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.