on 10-08-2006 9:13 PM
For our project we plan an test system(a copy of productive sytem). We do not expect any transport request from productive system).
There we will have some changes(transport requests) in workbench(less) and customizing(most of all) (e.g. Let say the request nr will be REP9000001 REP9000007).
We will release them prior to next copy of productive system copy and reimport them just after system copy.
However next transport on test system I assume will start again with REP9000001 and not REP9000008. Do you know how to move current entry in number range. I checked the usual table nriv but did not find suitable entry
Thank you in advance
Table - E070L.
Reset the transport number to whatever you want.
I hope this helps.
Regards
Cyrus
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
i think there is no Solution because you must inittialize
your Transportsystem after a hom. Systemcopy. There are
many Steps to do to get a useable System. There is only a
Problem if don't do that work. One of it is Transaction
se06 that changes your Sourcesystem.
Regards
Stefan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
81 | |
10 | |
10 | |
9 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.